01.03.2017

900 tonnes of steel from a scenery of ice and snow to Brazil

In early March, 29 trailer lorries, ten of which were wide loads, over weight or super tall, hit the roads in Finland. That is the number of vehicles needed to transport four Mantsinen 160 machines, of a total weight of ca. 900 tonnes, from the production plant to their destination. This time, the machines travelled from the scenery of snow and ice to their destination in Brazil.

The planning of massive logistics solutions is done much before the actual delivery. The machines were ordered to Brazil in the summer of 2016, and transport planning started four months before delivery, i.e. in December.

Full as possible

"That is when we start asking for preliminary offers and examining potential partners. After deciding on the partner, we start planning the delivery in more detail: loads are designed per each lorry, and the loads must be as full as possible. Meanwhile, we also make the shipping plan. Both operations require specific dimensions, weights and centres of gravity of each piece. The transport must be safe and economical," says project logistics coordinator Elena Mantsinen.

In delivery, investigating the circumstances at the destination is the most challenging element. Characteristics of the port, the unloading possibilities of the ship and possible further transport largely determine how the machine is dismantled for delivery.

Exotic destinations

In logistics solutions, the most important factor is the partners with the required knowhow. The forwarding agent is also in a a major role in transporting the machine safely from door to door. Exotic destinations add their own challenge. Brazil as destination had its own legislation, customs and documentation requirements which are different from Europe, for example.

Currently, four Mantsinen 160 machines are sailing the seas. They will travel from Finland to Brazil in about 4-5 weeks. Elena Mantsinen monitors their progress daily on her computer. In mid-April, the material handling machines should have arrived; two of them remain in the port and two will continue their journey to their final destination.

Once the machines have arrived, two technicians from the plant in Ylämylly travel to Brazil to mount and install the machinery. They make sure that everything works as agreed and the customer is satisfied with the delivery. That is when the Mantsinen team can sigh in relief.

More photos:





« Back
08.06.2017

Meet us in TOC Europe »

For Mantsinen, TOC Europe is a place to meet the people who matter.
18.05.2017

Participants from 25 countries at Mantsinen’s Dealer Days »

This time, Mantsinen 300 will be the focus of attention – the first deliveries will be with customers in the coming summer.
16.05.2017

Mantsinen appoints a new CEO »

The CEO of Mantsinen Group Ltd Oy will change on 1st July 2017.  
16.02.2017

Port of Norrköping Ordered Its Fourth Mantsinen Machine »

Port of Norrköping, one of Sweden's export harbours, will be strengthened in October when the fourth Mantsinen machine is delivered.
07.10.2016

Mantsinen moves closer to its customers by establishing a subsidiary in Sweden »

Mantsinen Group has established a subsidiary in Sweden. The aim is to serve local customers more efficiently and to improve the service experience of customers.
07.03.2016

Mantsinen to operate wood yard at Metsä Group's bioproduct mill in Äänekoski »

Metsä Fibre Oy, part of Metsä Group, and Mantsinen Group Ltd Oy logistics services have signed a contract on operating the wood yard of Metsä Group's bioproduct mill in Ää...
24.11.2015

MANTSINEN scoops IBJ “Crane of the Year” Award »

On November 16, 2015, MANTSINEN won “Crane of the Year” Award at the IBJ Awards in Antwerp, Belgium. The International Bulk Journal Awards is the night of the year for the maritime bulk in...
25.02.2015

Customer Report - No More Fuel Bills with Mantsinen 70 ER »

Ege Celik steel mill in Aliağa, Turkey has been using three electrically powered Mantsinen 70 ER material handlers since 2013. Two of the machines work in the port, unloading steel scrap from incoming...
20.10.2014

Superior fuel economy by Mantsinen »

In May 2012, Mantsinen 120 R HybriLift® was delivered to LFS – Lovisa Forwarding & Stevedoring, the port operator of Valko Port in Loviisa, Finland. For the first 5000 hours, Mantsinen 1...
01.10.2014

JT & Partners to represent MANTSINEN in Brazil »

MANTSINEN Group Ltd Oy has chosen JT & Partners as its dealer in Brazil. JT & Partners will represent the full range of Mantsinen hydraulic cranes and material handlers as well as spare parts ...
01.10.2014

Mantsinen Moves to Latin America »

Material Handling Machines-unit of Mantsinen Group extends sales organization to Latin America and opens up a sales office in São Paulo, Brazil. Mr. Samuli Seilonen has been appointed Regional ...
30.09.2014

Riga Central Terminal acquires Mantsinen 200 ES »

Riga Central Terminal (RCT) is acquiring a Mantsinen 200 ES HybriLift® material handling machine, which will considerably increase the company’s cargo handling efficiency. Expected delivery ...
26.09.2014

Mantsinen Dealer Meeting 2014 »

Mantsinen Dealer Meeting 2014 was held in Belgium. Huge thanks to everyone attending as well as to our customers, Cuypers Vorkliften Nv and Goeyvaerts-R. bvba, who opened their doors to us in Ant...
25.09.2014

Mantsinen 200 M to Cuypers Vorkliften Nv, Belgium »

In August 2014, Mantsinen Group Ltd Oy delivered a Mantsinen 200 M HybriLift® to Cuypers Vorkliften Nv, Port of Antwerpen, Belgium. This mobile Mantsinen harbour crane is used mainly for loading s...
14.02.2014

Ecological and economical Mantsinen 120 EM to Piteå »

ShoreLink, Piteå, Sweden, has two Mantsinen 120 EM which are part of the ports’ eco-friendly fleet ready to serve the customers. Mantsinen 120 EM HybriLift® features a mobile...
More: 1 | 2 |